What are the 4 P's of project management?

Asked by Sihemsmida, Last updated: Apr 18, 2024

+ Answer
Request
Question menu
Vote up Vote down

2 Answers

c.Dorothy

c.Dorothy

c.Dorothy
C.Dorothy

Answered Apr 18, 2018

The wrong statement is an activity cannot be represented by more than one arrow, but an arrow can represent one or more activities. When drawing an arrow flow chart for PERT/CPM, each event is a numbered circle. Each event can have multiple arrows coming from it with estimated times to complete that route.

For example, if you have an arrow between events 2 and 4 that would take 2 weeks, but the arrow between events 3 and 4 takes a week and a half, that means you have two ways you can get to event 4 that need to be done before event 4 is done. Each arrow represents one specific time frame between events. They don’t represent the events themselves.

upvote downvote
Reply 

sihemsmida

sihemsmida

sihemsmida
Sihemsmida

Answered Oct 26, 2017

An activity cannot be represented by more than one arrow but an arrow can represent one or more activities.
upvote downvote
Reply 

Advertisement
Advertisement
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader

Email Sent
We have sent an email to your address "" with instructions to reset your password.